p 355

Chapter 5

PolyLEVEL

®

Polyurethane Foam and Resin

APPENDIX 5B

MODEL SPECIFICATIONS

MODEL SPECIFICATION FOR

POLYURETHANE VOID FILLING OR

SOIL STABILIZATION APPLICATIONS

1

SCOPE

1.1 The work consists of designing, furnishing, and installing single-part, high-density polyurethane

material according to the project plans and this specification.

1.2 The parties and contract terms referred to in this specification are as follows:

1.2.1 The Owner is the person or entity that owns the facility or will own the facility once it is

completed. The Owner may have contractual agreements with, and be represented by,

other parties such as engineers, architects, or contractors that preform services under the

direction of the Owner. Where Owner is used in the specification, it refers to the Owner or

the Owner’s contracted representatives separate from the Installing Contractor.

1.2.2 The Installing Contractor installs the polyurethane material and possibly performs other

tasks associated with the project.

1.2.3 The Plans refer to the contract documents; including but not limited to the drawings and

specifications for the project.

1.3 The work may include void filling, stabilizing loose or sandy soil, or undersealing pavement and

faulted joints.

1.4 The Owner will provide suitable access to the construction site for the Installing Contractor’s

personnel and equipment.

1.5 Unless otherwise noted, the Installing Contractor shall provide all labor, tools, equipment, and

material necessary to accomplish the work.

1.6 Unless specifically noted otherwise in the contract documents, the Owner will remove and

replace structures, utilities, or other surficial improvements in the work area as necessary to

facilitate the work.

1.7 The Owner will be responsible for overall construction oversight to preclude the development of

unsafe conditions.

1.8 The Owner will be responsible for any soil density testing subsequent to the polyurethane

injection, unless otherwise noted.

1.9 The work does not include and post-installation monitoring unless specifically noted otherwise

in the contract documents.

2

APPROVED POLYURETHANE MANUFACTURERS

2.1 Foundation Supportworks

®

, Inc., 12330 Cary Circle, Omaha, NE 68128; Phone: (800) 281-8545;

Fax (402) 393-4002.