p 363

Chapter 5

PolyLEVEL

®

Polyurethane Foam and Resin

APPENDIX 5B

MODEL SPECIFICATIONS

10

CLEANUP

10.1 With one week of completion of the work, the Installing Contractor shall remove any and all

material, equipment, tools, debris, of other items belonging to the Installing Contractor or used

under the Installing Contractor’s direction.

11

METHOD OF MEASUREMENT

11.1 The high-density polyurethane material shall be measured by the pound. Weight of the injected

material will be recorded and documented at each location and at the end of each work shift.