APPENDIX 3D

MODEL SPECIFICATION – HYDRAULICALLY-DRIVEN PUSH PIER SYSTEMS

Chapter 3

Hydraulically-Driven Push Piers

8.1.6 Manufacturer’s published allowable system capacities for the pier assemblies, including

load transfer devices.

8.1.7 Calculated mechanical and theoretical geotechnical capacity of the proposed piers.

8.1.8 Minimum final drive and lock-off force requirements.

8.1.9 Structural lift requirements, if applicable

8.1.10 Minimum and/or maximum embedment lengths or other site specific embedment depth

requirements as may be appropriate for the site soil profiles.

8.1.11 Pier location tolerance requirements.

8.1.12 Load test procedures and failure criteria, if applicable.

8.1.13 Copies of certified calibration reports for load test measuring equipment to be used

on the project, if applicable. The calibrations shall have been performed within one

year of the proposed starting date for push pier installation or as recommended by the

equipment manufacturer.

8.1.14 Provide proof of insurance coverage as stated in the general specifications and/or

contract.

9

PIER INSTALLATION

9.1 Installing Contractor shall furnish and install all push piers per the project Plans and approved

pier design documentation. In the event of conflict between the project Plans and the approved

pier design documentation, the Installing Contractor shall not begin construction on any affected

items until such conflict has been resolved.

9.2 The Installing Contractor shall conduct their construction operations in a manner to insure the

safety of persons and property in the vicinity of the work. The Installing Contractor’s personnel

shall comply with safety procedures in accordance with OSHA standards and any established

project safety plan.

9.3 The Owner shall request marking of underground utilities by an underground utility location

service as required by law, and the Installing Contractor shall avoid contact with all marked

underground facilities.

9.4 The portion of the construction site occupied by the Installing Contractor, his equipment and his

material stockpiles shall be kept reasonably clean and orderly.

9.5 Installation of push piers may be observed by representatives of the Owner for quality assurance

purposes. The Installing Contractor shall give the Owner at least 24 hours’ notice prior to the

pier installation operations.

9.6 The push pier installation technique shall be such that it is consistent with the geotechnical,

logistical, environmental, and load carrying conditions of the project. The push pier shall be

positioned at the appropriate site survey location as determined from the plan drawings.

9.7 Push pier installation procedures specified in the manufacturer’s technical literature and/or code

agency approved evaluation report shall be followed.