4.5.2 Installation Steps

The following steps provide a broad overview

of a typical SmartJack system installation.

Intermediate steps, installation equipment and

tools used, and considerations for unusual

conditions or applications are not addressed.

Step 1

– Two-foot cube of soil is excavated

and backfilled with compacted crushed stone

(Figure 4.5.2.a1)

.

Step 2

– Pre-cast concrete or cast-in-place

footing installed above the crushed stone

(Figure 4.5.2.a2)

.

Step 3

– Galvanized steel tube is cut to the

appropriate length

(Figure 4.5.2.a3)

.

Step 4

– Steel column and components are

assembled and connected to the beam or floor

joists

(Figure 4.5.2.a4)

.