APPENDIX 2F
MODEL SPECIFICATIONS
Chapter 2
Helical Foundation Systems
11
EXECUTION
11.1 Installing Contractor shall furnish and install all helical soil nails per the project Plans and
approved soil nail design documentation. In the event of conflict between the project Plans
and the approved soil nail design documentation, the Installing Contractor shall not begin
construction on any affected items until such conflict has been resolved.
11.2 The Installing Contractor shall conduct their construction operations in a manner to insure the
safety of persons and property in the vicinity of the work. The Installing Contractor’s personnel
shall comply with safety procedures in accordance with OSHA standards and any established
project safety plan.
11.3 The Owner shall request marking of underground utilities by an underground utility location
service as required by law, and the Installing Contractor shall avoid contact with all marked
underground facilities.
11.4 The portion of the construction site occupied by the Installing Contractor, his equipment and his
material stockpiles shall be kept reasonably clean and orderly.
11.5 Installation of helical soil nails may be observed by the Owner for quality assurance purposes.
The installing contractor shall give the Owner at least 24 hours’ notice prior to the soil nail
installation operations.
11.6 Construction Procedure
11.6.1 The wall or slope is to be constructed from the top down as the soil in front of the wall
is removed to specified depths and the helical soil nails are installed at each level.
11.6.2 The exposed soil face shall be retained with a construction facing consisting of mesh
reinforced shotcrete or other appropriate facing material. Drainage systems, when
required, shall be installed prior to applying shotcrete or other facing material.
11.7 Site Drainage Control
11.7.1 Provide positive control and discharge of all surface water that will affect construction
of the helical soil nail retaining wall or slope. Maintain all pipes and conduits used
to control surface water during construction. Surface water drainage network shall be
independent of the wall drainage network.
11.7.2 Contact the Owner if unanticipated subsurface drainage structures are discovered
during excavation.
11.8 Excavation
11.8.1 Excavation shall proceed in stages or lifts according to the Plans, exposing a minimum
amount of soil face which will still allow for the installation of the helical soil nails and
wall facing system while assuring stability of the excavated face.
11.8.2 The Owner shall be responsible for providing the necessary survey and alignment control
during excavation of each lift and for performing the excavation in a manner which will
allow for construction of the wall facing to the specified minimum thickness and to the
line and grade indicated on the Plans. The Installing Contractor shall be responsible
for locating and installing the helical soil nails within the allowable tolerances in this
specification or on the Plans, and for performing the excavation and nail installation