10. Lifting of the existing foundation structure must be

verified by the registered design professional and

is subject to approval of the code official to ensure

that the foundation and superstructure are not

overstressed.

11. Field installation logs must be completed and

excavation pits or trenches must be backfilled and

compacted. Proper compaction procedures must

comply with the approved construction documents for

any site-specific requirement. When possible or as

required by the approved construction document,

grades or other means must be constructed to allow

proper, positive surface drainage away from the

structure.

4.2.4 New Construction Bracket Installation:

1. The helical pile must be installed in accordance with

Section 4.2.2 with an allowable angular tolerance of

± 1 degree from the vertical.

2. The top of pile elevation must be established and

must be consistent with the specified elevation. If

necessary, the pile can be cut off in accordance with

the manufacturer’s instructions at the required

elevation.

3. The new construction bracket must be placed over the

top of the pile, with the bracket cap plate in full, direct

contact (bearing) with the top of the pile shaft.

4. If the pile is used to resist tension forces, the new

construction bracket must be embedded with proper

distance into the footing or grade beam as required to

resist the tension loads as determined by a registered

design professional, and must be through-bolted to

the helical pile shaft with two bolts and matching nuts

as specified in Sections 3.2.2.2 and 3.3.5.3, and

installed to a snug-tight condition in accordance with

Section 4.2.2. Refer to Tables 2 and 3 for the proper

embedded edge distance requirements for the shaft

and bracket.

4.3 Special Inspection:

Continuous special inspection in accordance with Section

1705.9 of the 2012 IBC (Section 1704.10 of the 2009 IBC,

and Section 1704.9 of the 2006 IBC) must be provided for

the installation of foundation piles and foundation

brackets. Where on-site welding is required, special

inspection in accordance with Section 1705.2 of the 2012

IBC (Section 1704.3 of the 2009 and 2006 IBC) is also

required. Items to be confirmed by the special inspector

include, but are not limited to, the manufacturer’s

certification of installers, verification of the product

manufacturer, helical pile and bracket configuration and

identification, inclination and position of the helical pies,

the installation torque and depth of the foundation

piles, compliance of the installation with the approved

construction documents and this evaluation report.

5.0 CONDITIONS OF USE

The Foundation Supportworks, Inc. (FSI), Model HP288

Helical Foundation Systems described in this report

comply with the 2012 and 2009 IBC, and are suitable

alternatives to what is specified in the 2006 IBC, subject

to the following conditions:

5.1

The FSI helical foundation systems are

manufactured, identified and installed in accordance

with this report, approved construction documents

(engineering drawings and specifications), and the

manufacturer’s written installation instructions. In

case of conflict, the most stringent requirement

governs.

5.2

The FSI helical foundation systems have been

evaluated for support of structures assigned to

Seismic Design Categories A, B and C in

accordance with IBC Section 1613. Helical

foundation systems that support structures assigned

to Seismic Design Category D, E or F, or that are

located in Site Class E or F, are outside the scope of

this report, and are subject to the approval of the

code official, based upon submission of an

engineering design in accordance with the code by a

registered design professional.

5.3

Installations of the helical foundation systems are

limited to regions of concrete members where

analysis indicates no cracking occurs at service load

levels.

5.4

Retrofit and new construction brackets must be used

only to support structures that are laterally braced as

defined in Section 1810.2.2 of the 2012 and 2009

IBC (Section 1808.2.5 of the 2006 IBC).

5.5

The helical foundation systems must not be used in

soil conditions that are indicative of a potential

pile deterioration or corrosion situation as defined

by the following: (1) soil resistivity of less than

1,000 ohm-cm; (2) soil pH of less than 5.5; (3) soils

with high organic content; (4) soil sulfate

concentrations greater than 1,000 ppm; (5) soils

located in a landfill; or (6) soil containing mine waste.

5.6

Zinc-coated steel and bare steel components must

not be combined in the same system. All helical

foundation components must be galvanically isolated

from concrete reinforcing steel, building structural

steel, or any other metal building components.

5.7

The new construction helical piles (piles with new

construction brackets) must be installed vertically

plumb into the ground with a maximum allowable

angle of inclination tolerance of 0° ± 1°. To comply

with requirements found in Section 1810.3.1.3 of the

2012 and 2009 IBC (Section 1808.2.8 of the 2006

IBC), the superstructure must be designed to resist

the effects of helical pile mislocation.

5.8

The retrofit helical piles must be installed at a

maximum angle of inclination of 3.0 ± 1.0 degrees

from the vertical.

5.9

Special inspection is provided in accordance with

Section 4.3 of this report.

5.10

Engineering calculations and drawings, in

accordance with recognized engineering principles

as described in IBC Section 1604.4, and complying

with Section 4.1 of this report and prepared by a

registered design professional, are provided to, and

approved by, the code official.

5.11

The adequacy of the concrete structures that are

connected to the FSI brackets must be verified by a

registered design professional, in accordance with

applicable code provisions, such as Chapter 15 of

ACI 318 and Chapter 18 of IBC. The adequacy is

subject to the approval of the code official.

5.12

A geotechnical investigation report for each project

site must be provided to the code official for approval

in accordance with Section 4.1.1 of this report.

5.13

When using the alternative basic load combinations

prescribed in Section 1605.3.2, the allowable stress

increases permitted by material chapters of the IBC

(including Chapter 18) or the referenced standards

are prohibited.