2.12.3.2 Retro-Fit Helical Piers

Excavation:

• Hand or machine-excavate to expose the

bottom of the footing. Individual holes should

be approximately 3 feet square while a

continuous trench excavation should extend

at least 3 feet away from the structure.

• Depth of excavation should locally extend 13

inches below bottom of footing and 9 inches

back under bottom of footing where brackets

will be placed

(Figure 2.12.3.2.a)

.

Follow OSHA Trench Safety Procedures.

Failure to follow trench safety procedures

could result in death or serious injury.

Preparation of Footing:

• Notch spread footings 16 to 22 inches wide

(depending upon width of retrofit bracket)

and approximately flush with the face of the

foundation wall

(Figure 2.12.3.2.b)

. Thick

column footings or trench footings often

do not require notching of the concrete,

but should still be prepared so the face of

the footing has full contact with the back,

vertical plate of the bracket.

• Clean and prepare bottom of footing to allow

full contact and seating of the bracket.

Installation of Helical Pier:

• Attach lead section to drive head and

product adaptor.

• Place lead section’s first blade under the footing

and the shaft of the lead 1½ inches away from

bottom edge of footing

(Figure 2.12.3.2.c)

. This

will allow alignment of the lead to the required

angle of inclination of 3.0 ± 1.0 degrees from

vertical. As additional plates on the lead

section advance down the face of the footing

and pass the bottom of the footing, forward

crowd will be required to realign the shaft to the

appropriate inclination. In the case of a vertical

pile installation, a pilot hole is required to set

all plates of the lead below the bottom of the

footing before advancement of the pile. The

pile shaft is still set 1½ inches from the face of

the footing.

Figure 2.12.3.2.b

Footing preparation

Figure 2.12.3.2.c

Alignment of lead

Figure 2.12.3.2.a

Excavation at bracket