Chapter 3

Hydraulically-Driven Push Piers

CHAPTER 3

HYDRAULICALLY-DRIVEN PUSH PIERS

• The system is first equalized by opening

the valves at each cylinder in sequence and

adjusting the system pressure. The system

should be equalized to a pressure on the order

of 1,000 psi.

• Slowly raise the pump pressure to raise

the foundation. Monitor the lift at each pier

location and after achieving proper lift, close

the valve to the top of the cylinder. If the piers

are for stabilization only, close the valves as

soon as noticeable movement occurs.

• When the structure has been lifted to the

proper elevation or the piers reloaded to the

required lock-off load (typically the design

working load), the load is locked off to the

piers by tightening the two nuts down to the

top of the pier cap.

• The pressure is released from the hydraulic

system and the lift cylinder assembly is

removed from the bracket

(Figure 3.10.q)

. The

pier system installation is essentially complete.

Permanent benchmarks may be established

within and beyond the work area, if approved

by the owner or client. These monitoring points

would allow relative movements to be measured

in the future, if necessary

(Figure 3.10.r)

.

Step 7 Backfill and Clean Up Work Area

• Backfill excavations and properly compact

with a mechanical tamper

(Figure 3.10.s)

.

This may also be an ideal time to improve the

drainage system around structures with below

grade living areas or working space. New

drain pipe can be installed along with free-

draining granular backfill provided the drain

pipe is connected to an interior sump system

or drained by gravity to daylight discharge

points. Interior pier installation may require

concrete patching and finishing after soil

compaction

(Figure 3.10.t)

.

Figure 3.10.q

System locked off; pier installation complete

Figure 3.10.s

Backfill excavations and compact soil

Figure 3.10.t

Concrete placement at interior pier locations

Figure 3.10.r

Benchmark established with a

shallow hole drilled into the concrete block